A Slice of Paradise

The Pine Strawberry AZ Community Information Site

Home
Recent News
Something to Do
Road and weather info
American Pride
Recreation Activities
DPS Quilt Angels
Fuel Reduction
Business Directory
Worship Centers
Tonto Natural Bridge
Local Dining
Support our Sponsors
Website Sponsors
PSWID
Arizona DOT News
Volunteering
Classified Ads
Photo Gallery
P/S Elementary School
Isabelle Hunt Memorial Li
Senior Center Affairs Fdn
Community Calendar
Nature and Wildlife
Privacy Policy
Payson Regional Chamber o
Strawberry Elite
Tonto National Forest
Links
Tonto Rim Search and Resc
Contact Us
About Us
2010 Sock Hop
ADOT Reports on Highway 87 Improvements
 
This page will be updated as often as reports are received from ADOT.
 

 

  

Feb 19, 2010   

 

 


 January 29, 2010 This was the latest report received from ADOT

Arizona Department of Transportation
Rim Country Update
State Route 87 Safety Improvements Payson to Pine

 

What to expect the week of February 1:

 

SR 87 SAFETY IMPROVEMENTS - PAYSON TO PINE

 

Segment 1 - Just North of Payson between milepost 254.62 and milepost 255.94

Segment 2 - Just South of Pine between milepost 265.61 and milepost 266.69


SR 87 SAFETY IMPROVEMENTS - PAYSON TO PINE

Segment 1

Installation of Guardrail - Winter Shut Down

Crews will complete the installation of guardrail the week of February 1. Once the guardrail is installed, the project will go into winter shutdown. In the spring, crews will return to complete the paving operations and apply the final layer of asphalt. Rubberized asphalt will be used on SR 87 to increase life of roadway, reduce future maintenance costs, decrease roadway noise, and improve the overall quality of the roadway for a smooth ride. However, this type of asphalt can only be applied under certain temperature conditions to ensure it adheres to the first layer of asphalt properly. Work will resume in late April or early May when temperatures begin to increase. Applying the asphalt when temperatures are too low during winter months can compromise the quality of the installation.
The photo above shows where crews have started to
install guardrails along SR 87.
 
Please be aware that signs identifying the construction zone will remain in place during the shutdown, as seen in the photo to the right.


 



 

 


Home
  

ADOT strives to keep the public informed about construction projects, lanes restrictions, and closures.  This eUpdate is distributed periodically to help keep the Payson, Pine and Strawberry communities up to date and alert them of any expected construction activities that may affect traffic. 

 

Stay in touch with the project team by calling the project hotline at 1.877.521.1118 or
emailing
PrescottDistrictUpdates@azdot.gov.

  
Please note: Changes to construction plans can happen frequently due to weather, equipment availability and personnel issues. We try to anticipate construction activities a week in advance but changes may occur. Intermittent lane closures, with short delays, may not always be known in advance.